PMP Problem,Tell me the answer and the reason.
You are working on a large construction project that is progressing within the baselines.Resource usage has remained steady,and your boss has just awarded you a prize for your performance.One of your team members returns from a meeting with the customer and tells you that the customer is not happy with the project progress.What is the FIRST thing you should do?
A.Tell your manager.
B.Complete a team building exercise and invite the customer's representatives.
C.Change the schedule baseline.
D.Meet with the customer to uncover details.

PMP Problem,Tell me the answer and the reason.You are working on a large construction project that is progressing within the baselines.Resource usage has remained steady,and your boss has just awarded you a prize for your performance.One of your team
D. Meet with the customer to uncover details.
你应该找一个能解决问题的选项.对于项目经理来说,选项A不够主动.在和你的经理谈论之前,你也需要更多的信息.选项B不错,但是它没有说明客户对项目的担心.改变基准(选项C)在本题中是不道德的.问题解决从定义问题的原因开始,所以选项D是对的.

PMP,Tell me the answer and whyOne of your employees is up for promotion.If the promotion is granted,the employee will be reassigned elsewhere causing a problem for you on your project.You can delay the promotion until your project is complete.You sho PMP Problem,Tell me the answer and the reason.A project manager discovers a defect in a deliverable that is due to the customer under contract today.The project manager knows the customer does not have the technical understanding to notice the defect PMP Problem,Tell me the answer and the reason.You are working on a large construction project that is progressing within the baselines.Resource usage has remained steady,and your boss has just awarded you a prize for your performance.One of your team Please tell me what's the problem.Please tell me what's the problem.Please tell me what the problem is. Please tell me the environmental problem in China can you tell me the s_____to solve this problem 快 Tell me about a problem you had with a supervisor Can you tell me thing abaut friendship?About friengship problem Can you tell me ____ ____ ____ ____the maths problem? Please tell me the solution to the problem.改写句子Please tell me ___ ___ ___ the problem. Could you tell me how I can deal with the problem?[同义句转换]Could you tell me how[][][]the problem? Can you tell me how I can solve the problem quickly(改为同义句)Can you tell me ____ ____ _____the problem quickly Can you tell me how I can work out the problem?句型转换.Can you tell me ____ ____ work out the problem. Tell me tell me . Can you tell me who ___(talk)to and where____(get)help when we have problem? can you tell me what your ______ (big ) problem is 用适当形式填空 could you tell me how to deal with this problem?的同义句 Tell me about a complex problem you had to deal with.